Timing

  • 2020
    Appointment of design team
  • Spring 2023
    Final design
  • Autumn 2024
    Temporary closure of town hall. Tourist reception, the city council , official receptions and weddings are moving.
  • Early 2025
    Preparatory works
  • October 2025
    Start of renovation works
  • In 2029
    Opening of the renovated city hall